New CCGT power generation station, 826MW capacity in Agios Nikolaos


  • Secondary additional works for the completion of the erection of systems and equipment for the project and their handover for commissioning.
  • Procurement, manufacturing, and erection of additional supports for piping systems.
  • Erection of sampling & dosing, partial fire fighting piping systems, modifications to existing steel structures of buildings, and execution of peripheral erection works for bop equipment.
  • Erection of the compressed air network and the temporary piping cleaning networks.
  • Execution of auxiliary disassembly/restoration works and non-destructive testing for the chemical cleaning and steam blowing processes of the project.
  • Undertaking the entirety of the works and providing site warehouse management services for the project through the provision of machinery and personnel. 